Roads:
- The Grader at Kleinmond is not operational. It is in for repairs but will only be operational again in 3 months – hopefully!
- A contractor has been appointed to assist with the grading of the roads in Betty’s Bay. No time frame has been given for this process to start.
- In the meantime, potholes are filled and rolled as far as possible. However, gravel is limited.
- Most of the first 500 cubic metres has already been used in January/mid-February 2026. Another 500 cubic meters has been ordered and should be delivered soon.
Storm Water:
- The Kleinmond team is busy with storm water drainage systems, with Pearl and Luckhoff Roads the priority
Amund Beneke